GTG Works – IRAQ, Badra CPF Phase 2 Project

Project Info

  • Construction Date

    28th, February, 2015 to 31, March, 2017

  • Category

    Ongoing Projects

  • Client Name

    Samsung Engineering/Gazprom Neft Badra

  • Project Location

    Badra Oilfield – Wasit, Iraq

  • Current Progress

    95%

IMG_20160625_070934

Project Information

Al Dar International has been contracted for installation of 5 Gas Turbine Units with Total capacity of 125MW for the Central Processing Facility Phase 2 Project at Badra Oil Field, Iraq. The scope of Work including but not Limited to Installation of Mechanical, Electrical, Instrument and interconnection Piping, with all related Pre-commissioning Work;

  • Preparation of Civil Works (Chipping and Padding)
  • Installation of generators/Gas Turbine, LOM, Stacks, Cooler fans and all related equipment and Pumps
  • First Alignment
  • Final Alignment
  • Pre Commissioning
  • Start up And Commissioning

 

Power Generation Sets


  • Gas Turbine
  • Lube Oil Module (Oil Tank + Gear)
  • Generator
  • Gas Turbine Enclosure
  • Control Compartment – 1
  • Control Compartment – 2
  • Generator Aux Cubicle
  • CO2 Fire Fighting container
  • Compressor Water Washing Pump Skid
  • Miscellaneous
  • Inlet air System
  • Exhaust System
  • Stack
  • Lube Oil Cooler
  • Lube Oil Mist Separator
  • Bearing Cooling Fan