Badra CPF 2-Project – Electrical Works

Project Information

Al Dar International has been contracted to do Electrical Installation for the Central Processing Facility 2 at Badra Oil Field, Iraq.

 

Scope of Work


The electrical installation involved the following activities:

  • Development of detailed engineering as required.
  • Definition of exact location of bulk equipment, cable routing, actual cable lengths,
  • Location, shape and dimensions, of supports and bracket for cable trays, cables, conduit non itemized equipment, junction boxes, etc.
  • Installation of the following Equipment:
    • Emergency Diesel Generator, (B) H.V & L.V Switch board & MCC/Lighting/Auxiliary
    • Panel, (C) Transformer/Capacitor/GIS ,( D) Battery & Charger/UPS
  • Installation of the following Apparatus:
    • Laying of cables for more than 1.5 million meters with all termination and glanding as required.
    • Lighting fixture:
      • Weather Proof/Explosion Proof, (b) Indoor (in building general purpose type)
      • Push button station
      • Weather Proof/Explosion Proof, (b) Indoor (in building(
      • Receptacle
      • Weather Proof/Explosion Proof (b) Indoor (in building general purpose type)
    • Communication System – Paging and set/Amplifier/Speaker/Public Address/Computer Network
    • Fire Alarm System, and other activities.

 

Badra CPF 2-Project – Mechanical Works

Project Information

Al Dar International has been contracted to do Mechanical Equipment installation for the Central Processing Facility 2 at Badra Oil Field, Iraq.

Scope of Work


The project included and not limited to:

Rotating Equipment
  1. Gas Compressor installation
  2. Gas turbine Installation
Stationary Equipment
  1. TEG Contactor Column.
  2. Installation of Columns.
  3. Installation Different size of pumps.
  4. Installation of different size of heat exchangers.
  5. Installation of different size of vessels.